In July we continued the RC work on higher levels of the building. We also continued erecting the curvilinear steel wall in the central part of the building, proceeded with cover-up operations and carried on water and heat insulation of external walls.
We began work on the linear drainage of the museum’s external fire escape cases. Heating systems are now also being mounted in those cases. In addition, masonry work began in the technical part of the museum building. We also started installing mineral-wool acoustic insulation along the ceiling at Level 208 (underground).